Scheduling
Timeline and progress tracking tools for project schedules.
A bar chart illustrating the project schedule with start/finish dates and dependencies.
Key Features
- Horizontal bars: Task duration along a timeline
- Dependencies: Arrows showing relationships (FS, SS, FF, SF)
- Milestones: Diamond shapes for key dates
- Critical Path: Highlighted longest path through the project
- Progress: Shading within bars to show percent complete
The most commonly used scheduling tool. Generated by MS Project, Primavera, and other tools.
A simplified Gantt chart showing only key deliverables, events, or dates.
Characteristics
- Significant events with zero duration
- Ideal for executive reporting and stakeholder communication
- Does not show task durations or dependencies
- Used in status reports and project dashboards
Milestones typically represent: kickoff, phase gates, deliverable completions, approvals, go-live, and closure.
Tracks work remaining vs. time in an Agile sprint or iteration.
How to Read It
- X-axis: Time (days in the sprint)
- Y-axis: Work remaining (story points or tasks)
- Ideal line: Straight diagonal — expected burndown
- Actual line: Real daily progress
Patterns
- Above ideal: Behind schedule
- Below ideal: Ahead of schedule
- Flat sections: Work blocked
- Upward spikes: Scope added mid-sprint
A Burnup Chart is the inverse — shows work completed, making scope changes more visible.